October 27, 2009: Contruction is underway!

These are the contractors building your new library.

The final contracts, Contracts 6-10, were just awarded on October 13, 2009, by the Library
Board of Trustees to the following contractors:

 
Contract 6 - General Construction Work
Key Interiors, LLC of Poughkeepsie, NY 
 
Contract 7 - Plumbing Work
Dutchess Mechanical Inc. of Hopewell Junction, NY 
 
Contract 8 - Fire Protection Work
SRI Fire Sprinkler, LLC of Highland, NY 
 
Contract 9 - HVAC Work
Crisafulli Brothers Plumbing and Heating
Contractors, Inc. of Albany, NY

 
Contract 10 - Electrical Work
Comalli Electric of Albany, NY
The pre-construction work for Contracts 1-5 is complete.
 
Contract 1 - Selective Demolition and Site-work
J. Mullen and Sons, Inc. of Saugerties, NY
 

Contract 2 - Hazardous Material Remediation
Neoplanta Restorarion, Inc. of Clifton Park, NY
 
Contract 3 - Geothermal Test Well and Conductivity Test
Boyd Artesian Well Drilling Company of Carmel, NY
 
Contract 4 - Geothermal Well Installation
Geothermal Services of Mays Landing, NJ
 
Contract 5 - Construction Easement Selective Demolition and Site-work
J. Mullen and Sons, Inc. of Saugerties, NY

 

 

 

 

 

 

 

 

 

 

GroundbreakingOctober 1, 2009 Groundbreaking

Saugerties Library Board of Trustees and Director Jessica Serrano at the groundbreaking ceremony that was held on Thursday,September 24, 2009.  The ceremony wasattended by over 75 people.  Those in attendance included Senator John Bonacic and Assemblyman Peter Lopez. Thank you to all those who joined in our celebration.

View more photos here.

Monday, August 10, 2009

On Monday, August 10, 2009 Geothermal Services, Inc., of Mays Landing, New Jersey, will begin setting up to drill 20 Geothermal, heating and cooling, wells.
 
Divsion Street Closing
Division Street will be closed on Monday, August 10, 2009 for the remainder of the Library construction project. The closure will take place between the intersection of Washington Avenue and for approximately 100 feet along Division Street.

Friday, August 7, 2009
 
Thank You to the Saugerties Central School District Board of Education for granting approval of the Construction Easement that will allow the Library to proceed with the construction project along the Cahill Elementary School property.

July 7, 2009

Traffic Plan
 
A Traffic Plan has been developed in conjunction with the Village Police Department to minimize the impact of the project on the surrounding neighborhood. It was presented to the Village Board on June 1 and approved by the Board on June 15, 2009.
 
To view the Traffic Plan logistics click here.
To view the Traffic Plan design click here.
 
Geothermal Well Testing
 
One Geothermal Test Well is being drilled on the Library's property between July 7 and July 15. Drilling wells is fairly loud and we apologize for any inconvenience this may cause. This work is critical to the pre-construction phase of the project and will be completed as quickly as possible.